Description

An earth settlement under a single-family residential building resulted in the total stripping of a footing and partially of the facade wall. Artur Peixoto Lda. was responsible for the design and execution of the structure's recovery using micropiles. The greatest difficulty was the access and confinement of the work space, overcome with the use of small equipment.

Client

House owner

Location

Galegos, Barcelos

Special works

  • Execution design
  • 1 DPSH test
  • 5 micropiles N80-76x6mm
  • Reinforced concrete