Cruise Port of Leixões
Description
The project consisted of the implementation of the retaining wall in the construction of Cruise Terminal and the Pole Sea of University of Porto, located on the south pier the Port of Leixões.
The solution has a linear development of 305 meters and 5 meter excavation. The retaining wall was materialized by Cutter Soil Mixing panels (CSM) armed with metal sections IPE and N80 tubes.
Project Owner
Port of Leixões
Contractor
Ferreira Build Power
OPWAY
Location
Matosinhos, Portugal